San Francisco International Airport Terminal 2/Boarding Area D Rehabilitation

Diamond Level – Vertical Project $25-$500M 

San Francisco Int’l Airport Terminal 2/Boarding Area D Renovation

  • (Owner) City and County of San Francisco – Airport Commission
  • (Prime) Turner Construction Company
  • (Designer) Gensler Architects
  • (CM) T2 Partners
  • (Facilitator) OrgMetrics

Photo Gallery

Project Information

Airport PM: Ray Quesada
Construction Manager: Geoff Neumayr (T2 Partners)
Prime Contractor PM: Kavendar Singh (Turner)

Original Project Budget: $400 mi
Final Project Budget: $398 mi

Original Project Days: 650
Actual Project Days: 760

DRB/Claims: None
Cost Savings: $1.15 mi 

Project Details: 640,000 sq ft Terminal 2 Building for Virgin America and American Airlines. First Airport Terminal in the United States to reach LEED Gold® designation.

Project Challenges: SFO’s first D/B Project constructed on an aggressive timeline to finish several months early – all without impact on traveling public.  More than 18 Stakeholders were involved in Partnering Meetings from Design through Construction.