Sacramento International Airport ‘Big Build’ – Terminal B

2012 Diamond Level Partnered Project of the Year Award – Vertical Mega Project

  • (Owner) County of Sacramento
  • (Landside Prime) Austin Walsh Construction J.V.
  • (Airside Prime) Turner Flatiron in Association with Teichert Construction J.V.
  • (Designer) Corgan Associates in Assoc. with Fentress Associates
  • (CM) AECOM
  • (PM) Paslay Management Group
  • (Facilitator) Aviation Innovation, LLC

Photo Gallery

Project Information

Airside CM: Gary Ralls - PM: Otto Randoph
Landside CM: Tom Skinner - PM: Bill Fenton

Original Project Budget: $687 mi
Final Project Budget: $675.5 mi

Original Project Days: 1323
Actual Project Days: 1204

DRB/Claims: None
Cost Savings: $12 mi

Project Details: $1B program included a 669,000 sq ft Terminal and Concourse buildings with LEED Silver Certification features, an $8M Art program, a 19-gate concourse, and an Automated People Mover system.

Challenges: The Airport accelerated the schedule by 4 months to complete the project in October, 2011, requiring resolution of the overnight move of Airlines, TSA, and CBP (Custom Border Protection) in order to meet new the timeline.